Q#1 Economic Load Dispatch GATE EE 2012 MCQ +1 mark -0.33 marks

The figure shows a two-generator system supplying a load of, connected at bus 2.         

The fuel cost of generators  and  are:

and and he loss in the line is, where the loss coefficient is specified in p.u on a 100MVA base. The most economic power generation schedule in MW is

Explanation Locked!

Unlock this branch to view the explanation, track, bookmark and more.

Sign in to Unlock
Browse Practice Questions by Chapters / Topics in Browse Practice Questions by Chapters / Topics in GATE Electrical Engineering
Total Questions

Attempted

% Attempted

Correct

% Correct

Topic Questions Attempted Correct
Network Analysis 260 0 0
Signals and Systems 165 0 0
Control Systems 258 0 0
Analog Electronics 184 0 0
Digital Electronics 148 0 0
Electrical Machines 392 0 0
Power Electronics 237 0 0
Power Systems 344 0 0
EMFT EE 107 0 0
Measurement 158 0 0
Engineering Mathematics 225 0 0
General Aptitude 211 0 0