Q#1 Economic Load Dispatch GATE EE 2025 NAT +2 marks -0 marks

Two units, rated at 100 MW and 150 MW, are enabled for economic load dispatch. When the overall incremental cost is 10,000 Rs./MWh, the units are dispatched to 50 MW and 80 MW respectively. At an overall incremental cost of , the power output of the units are 80 MW and 92 MW, respectively. The total plant MW-output (without overloading any unit) at an overall incremental cost of  is __________ (round off to the nearest integer).

Explanation:

Given: For     &

For

Let

 

For lossless system,

  &

 

 

 

 On solving,

for   &

 

 

 

On solving,

Now,  Rs/ MWh,

 

                 

 

                 

Since,

Thus,

Total plant Mw -output without overloading any 

Browse Practice Questions by Chapters / Topics in Browse Practice Questions by Chapters / Topics in GATE Electrical Engineering
Total Questions

Attempted

% Attempted

Correct

% Correct

Topic Questions Attempted Correct
Network Analysis 208 0 0
Signals and Systems 21 0 0
Control Systems 18 0 0
Analog Electronics 10 0 0
Digital Electronics 138 0 0
Electrical Machines 17 0 0
Power Electronics 17 0 0
Power Systems 18 0 0
EMFT EE 8 0 0
Measurement 6 0 0
Engineering Mathematics 27 0 0
General Aptitude 104 0 0